Page 1 of 1

Batch Job Last Run Time Cleared

Posted: April 21st, 2022, 8:45 am
by CathyC
In the batch jobs page, when you change the schedule, the last run time is cleared. I think it should be retained because its still relevant to know when it last ran
Batch Job last run time cleared.PNG

Re: Batch Job Last Run Time Cleared

Posted: April 22nd, 2022, 9:42 am
by SteveCap
The reason we clear it is because we wanted to make sure the new schedule runs at least once. If it stays set it is possible to edit the schedule in a way were it would never run again. I have created task #10370

Re: Batch Job Last Run Time Cleared

Posted: May 5th, 2022, 3:15 pm
by JustinVanRegenmorter
This feature request has been added as of DesignTime Revision 2272 and RunTime Revision 964.